Had a call from my site supervisor saying hes back from holidays and informs us that plastering will start in a couple of days, this house so far is flying along.
Had a email from customer care saying brickwork will be finished my Jan 24th and we will be in lock up. wowww
Call me nuts .. on sat i went down to the house and swept the lower frames of saw dust and mess .Dont know wether the plasterers clean it before they plaster the walls but didnt want them to plaster up the mess in side them .
Will have to call kevin and ask him wether hes been in touch with PD and informed them of the issues that need to be fixed especially the plumbing
The electrician has been and put in the cables and wiring fone points but noticed there wasnt a power point in the ensuite and bathroom damm forgot to tell the site supervisor.
ductwork has been roughed in and will be finished this week with the insulation.
I cant believe how smooth this has all gone ... no major headaches thankgood ness .. cross fingers and knock on wood everything else will go well after lock up.